Metal Shear Blade Replacement System

Project

Western Metals Recycling's metal shear blades are maintained or changed approximately every 2 weeks. This process is currently labor intensive and unsafe. The purpose of this project was to design and build a system or procedure to increase the speed and safety of the process, while reducing the amount of effort needed. The design requirements are as follows

an old building a stand
  • $5000 Budget Run on electrical, pneumatic, or hydraulic power
  • Maintain operator safety
  • Function within space constraints of shear
  • Remove and replace shear blades
  • Operators should not be required to lift more than 50
  • Device must be able to function in temperatures from 20 F to 110 F and Any weather condition

Design Description

  • This project consists of three different systems, the scissor table, crane arm/base, and the pusher puller.
  • All components are built using steel to withstand the forces of blade moving and replacement

The systems of project design and their functions:

  • The scissor table is moved into place in the shear throat, used to lift and lower blades to working heights safely
  • The crane arm is used to move blades to and from shear mouth
  • The pusher puller is used to remove the blades by placing the collet inside the blades; force is then applied to the center line of the pusher puller to remove blades
3D model
3D model
3D model of metal shear
metal shear
diagram
metal shear
metal shear

Performance Review

metal shear being replaced
  • Most of the tests performed on this device were done using field tests at WMR
  • Test not performed in the field were done using calculations with known forces from loading conditions
  • The performance of required lifting force was done by determining the maximum load required by the technician during a blade change.
Parameter Targets Threshold Actual Performance
Time to complete blade change (hours) 3.5 7 4
Manual Force required by Technician (lbf) 50 100 60
Force to tip while holding blade (lbf) 100 25 52.27
Operator distance from blade during operation (ft) 1 3 1 – 1.5
Lateral motion for blade alignment (in) 3 0 30+
Rotational motion for blade alignment (deg) 5 0 5
Static height in between phases (ft) 3.5 2 4-1
Number of steps to complete flip 2 5 4
Number of mechanical inputs to complete process 3 7 5
Number of steps to reconfigure for pulling collars 2 7 N/A

Conclusion

This project was able to produce a working prototype of the system to WMR that met the needed requirements. These results are shown in the Performance section. The follow came as results of this project

  • Working system capable of assigning with shear blade replacement
    • All 3 systems working, Scissor Table, Crane Base and Arm, and the Pusher Puller
  • Lessons Learned
    • Clear definition of desired results allows for a clearer design path to a solution
    • Understanding the customers desires for the project is critical to a good design for the customer
  • Recommendations for future work
    • Hydraulic device to push the top blades out without the need of an electric jackhammer
    • Decreasing weight of design by building device for single blade removal instead of both blades
    • Adding hydraulic cylinder to crane arm to allow for less manual effort in the blade changing process
College of Engineering UtahStateUniversity

Shane Canfield (shane.canfield@usu.edu), Nate Rowley (nate.rowley@usu.edu), Josh Fonger (joshua.fonger@usu.edu), Eric Larsen (eric.michael.larsen@usu.edu), Jared Christiansen (jared.christiansen@usu.edu)