Wilcox Wakeboarding Park: A Boatless Wakeboarding Experience
Team: Henry Barth, Braden Christensen, Mason Lunt, Aaron Mackliet, Ryan Ranere, and Blake Wilcox
Sponsor: JUB Engineering Inc.
Project Summary
Project Overview: Design of cable wakeboarding pond and clubhouse in Syracuse, Utah. The purpose of this project is to provide additional outdoor recreational space to the growing community and to create a state-of-the-art facility to attract global tourists to stimulate the local economy.
Figure 1. The project site (~37 Acres) is located at 700 S 3000 W, Syracuse, UT.
Project Scope: Tofu-Dreg Engineering provided designs for the wakeboarding pond, sediment removal process, cable tower design, and park clubhouse design.
Figure 2. Concept Sketch of Park Clubhouse
Project Deliverables: Project deliverables included construction drawings, details, and calculations for the pond, cable towers, and clubhouse to the client.
Criteria & Selection Process
Alternative Selection Criteria: Tofu-Dreg Engineering developed several different alternatives for liners and towers and evaluated the alternatives against the weighted criteria below:
Cost (20%)
Constructability (15%)
Durability (30%)
Aesthetics (35%)
Alternatives
Pond Liner Alternatives: The team explored the use of the following different liners in the design process:
- High-Density Polyethylene
- Pros: Durable,
- Cons: Difficult to install
- Polyvinyl Chloride
- Pros: Low Cost
- Cons: Not durable
- Ethylene Propylene Diene Monomer
- Pros: Easy installation
- Cons: Semi-high cost
- Concrete
- Pros: Durable
- Cons: Expensive
Tower Alternatives: Tofu-Dreg Engineering explored the use of two different tower geometries in the design process:
- Steel A-frame
- Pros: Easy assembly, lower cost
- Cons: No multi-tower tracks
- Steel Space Frame
- Pros: Multi-tower tracks
- Cons: Difficult assembly
Figure 3. Concept Sketch of Space Frame (Left) and A-frame (Right)
Sediment Removal Alternatives: For this project, the team explored different alternatives for cleaning the water before releasing to the pond.
Figure 4. Hydrodynamic Separator (TRCA)
- Hydrodynamic Separator
- Pros: Small
- Cons: Requires elevation head
- Sedimentation Pond
- Pros: Has desired aesthetics
- Cons: Large construction cost
Selected Alternative
Selected Pond Liner: EPDM Liner
- Estimated Cost: $5.5 million (Entire Pond Construction)
Selected Alternative: Sedimentation Pond
- Estimated Cost: $340,000
Selected Tower Geometry: A-Frame
- Estimated Cost: $500,000
Final Design
Final Pond Design: The final pond design area is 9.2 acres, has an average depth of 8.5 ft, and will require 148,000 yd³ of earth to be excavated. The excavated earth will be stored in the southern part of the project site and sold as topsoil.
Figure 5. Plan View of Pond Design. (Note: Sediment Pond on North East, and Park Clubhouse on South End of Pond)
Final Tower Design: The final pond tower design is made of 10 inch square hollow steel sections. A pair of towers is designed to span cables up to 450 feet across the pond. Each tower leg sits on 30” diameter concrete foundations.
Figure 6. Final A-frame Tower Design
Acknoledgements
- Adam Hess
- Bryce Wilcox, PE
- Colin Phillips, PhD
- Austin Ball, SE
- Josh Peters
- JUB Engineers Inc.
- Our Wives